Category
Utility
Client
DC Water and Sewer Authority
Location
Washington, D.C.
Key Challenges & Project Details
- Modifications to combined sewer chambers and installation of 12 inflatable dams within the combined sewer system in various locations throughout Washington, D.C.
- The dams, approx. 12’ x 30’, are equipped with complex instrumentation systems which sense flow levels within the combined sewer chambers, inflating and deflating as appropriate during rain and non-rain periods
- Installed concrete pads, air piping, mechanical/electrical equipment, piping, valves, conduit, junction boxes, instruments and other devices at eight locations
- Deep excavations were required—up to 30’ in depth and 20’ in length within city streets
- Existing pipe lines were supported within each excavation and cast-in-place concrete structures 80 CY+ in volume were constructed over pipes up to 84″
- Installed approx. 220 LF of 10″, 12″ and 15″ sewer pipe, a 60″ diameter sewer manhole, a 72″ sewer manhole flow diameter and bypass pumping of sewers up to 78″ diameter to allow connection
- Most sites were in heavily traveled roadway
- Required extensive planning for traffic control, utility relocations and other areas of construction
- Pavement, curb, sidewalk and other disturbed areas were restored after dam and sewer modifications were complete
- Many safety considerations such as confined space entry, preparation for storm events and personal protective equipment
- Several of the sites are heavily influenced by tidal flow of the Anacostia River
- Temporary bulkheads equipped with “flap gates” to protect the work zone from tidal flow while still allowing storm water to run through were field fabricated
- Inserting and maneuvering the Fabridams through the sewer chambers was accomplished with custom lifting/winching/jacking/rolling devices
- Corman completed the project successfully and on time