Category
Utility

Client
DC Water and Sewer Authority

Location
Washington, D.C.

Key Challenges & Project Details

  • Modifications to combined sewer chambers and installation of 12 inflatable dams within the combined sewer system in various locations throughout Washington, D.C.
  • The dams, approx. 12’ x 30’, are equipped with complex instrumentation systems which sense flow levels within the combined sewer chambers, inflating and deflating as appropriate during rain and non-rain periods
  • Installed concrete pads, air piping, mechanical/electrical equipment, piping, valves, conduit, junction boxes, instruments and other devices at eight locations
  • Deep excavations were required—up to 30’ in depth and 20’ in length within city streets
  • Existing pipe lines were supported within each excavation and cast-in-place concrete structures 80 CY+ in volume were constructed over pipes up to 84″
  • Installed approx. 220 LF of 10″, 12″ and 15″ sewer pipe, a 60″ diameter sewer manhole, a 72″ sewer manhole flow diameter and bypass pumping of sewers up to 78″ diameter to allow connection
  • Most sites were in heavily traveled roadway
  • Required extensive planning for traffic control, utility relocations and other areas of construction
  • Pavement, curb, sidewalk and other disturbed areas were restored after dam and sewer modifications were complete
  • Many safety considerations such as confined space entry, preparation for storm events and personal protective equipment
  • Several of the sites are heavily influenced by tidal flow of the Anacostia River
  • Temporary bulkheads equipped with “flap gates” to protect the work zone from tidal flow while still allowing storm water to run through were field fabricated
  • Inserting and maneuvering the Fabridams through the sewer chambers was accomplished with custom lifting/winching/jacking/rolling devices
  • Corman completed the project successfully and on time